The Sydney Metro West project is a new 24-kilometre metro line with stations confirmed at Westmead, Parramatta, Sydney Olympic Park, North Strathfield, Burwood North, Five Dock, The Bays, Pyrmont and Hunter Street in the Sydney CBD.

Delta Group has been contracted by Sydney Metro to deliver the Enabling Works package to prepare the sites at the future Parramatta and Westmead metro stations and Clyde stabling and maintenance facility.

This package of works will include:

  • Site Establishment Works
  • Service Disconnections & Relocations
  • Hazardous Materials (HAZMAT) Removal
  • Internal Strip Out of Structures
  • Demolition of Existing Structures
  • Site Clearing