Cut and lift demolition of a 200m2 slab with a catchdeck over a neighbouring property’s basement access ramp, including polystyrene filled precast panels laid across precast beams
High volumes of double RPEQ certified temporary engineering, with the entirety of site works involving a suspended slab
Structural demolition of 4,000m2 precast basement over the Brisbane River, involving multiple crane locations, concrete cutting, and innovative working platforms
Key Challenges
Floating barge and upskilling of operators with commercial marine cox tickets; utilising floating walkways to ensure access at all tide levels
Mobilising 300t mobile crane across 12 separate lifting locations, including custom built hanging scaffold structure and wiresaw platforms
Demolition of pedestrian bridge and bridge landing over a CBD street, footpath and adjacent retail businesses