Tweed Valley Hospital

Lendlease

Sector: Urban, Health & Aged Care

  • >56,000Total Workhours
  • 2.2kmStormwater Drainage
  • 1.8kmAshphalt Roadworks
  • 4,000m²Ashphalt Carpark Construction
  • 6.9kmServices Trenching
  • 5,500m²Pavement Demolished
  • Social Procurement
  • Piling Platform & Proof Digging
  • Shotcrete Walls
  • Ground Anchors
  • Propping
  • Foundation Piles
  • Detailed Earthworks
  • Pad Footings
  • Pile Caps
  • Lift Rafts
  • Site Dewatering
  • Slab Preparation
  • Waterproofing
  • Stormwater & Drains
  • Roads & Pavements
  • Kerbs
  • Traffic Management
  • Enviro Monitoring & Controls
  • Stakeholder Engagement
  • Materials Solution Management
  • Site Preparation
  • Bulk Earthworks
  • Retention Systems
  • Groundwater & Leachate

Unique Attributes

  • Large Scale Bulk Earthworks (cut to fill and cut to stockpile): >100,000m3 and including import of gravels
  • High level social procurement targets: >50% of labour hours from (immediate) local subcontractors, plus 25% of contract spend with Indigenous contractors/workers
  • Large Gabion Walls construction – 500m long and up to 3.5m high

Key Challenges

  • Very high strength basalt rock throughout majority of site footprint
  • Site remediation and clearing
  • Site dewatering – sub tropical site climate conditions, with more than 1,600mm of rainfall occuring throughout works programme