Sydney Metro City – Martin Place

Transport for NSW

Sector: Urban, Public Infrastructure

  • >82,000Total Workhours
  • >154,000tSandstone Excavated
  • >36,000C&D Waste Removed
  • 50+Total Workforce at Peak
  • >68,000Pedestrians Per Day Adjacent to Both Sites
  • >95%Resource Recovery Rate – Both Sites
  • Permits & Authorities
  • Surveys – Geotechnical
  • Survey – Cultural & Heritage (incl. Archaeological)
  • Enviro Monitoring & Controls
  • Cultural & Heritage Protection
  • Piling Platform & Proof Digging
  • Retention Piles
  • Ground Improvement
  • Capping Beams
  • Site Remediation
  • Loading Platforms
  • Shotcrete Walls
  • Ground Anchors
  • Soil Nails
  • Detailed Earthworks
  • Pad Footings
  • Site Dewatering
  • Crane Base Construction
  • Inground Services
  • Slab Preparation
  • Retaining Walls
  • Stormwater & Drains
  • Security
  • Hazmat Removal
  • Strip Out
  • Manual Demolition
  • Mechanical Demolition
  • Long Reach Demolition
  • Robotic Demolition
  • Cut & Lift Demolition
  • Scaffold
  • Gantries
  • Hoardings
  • Traffic Management
  • Heritage Protection
  • Services
  • Cranage & Rigging
  • Propping & Bracing
  • Temp Works Engineering
  • Stakeholder Engagement
  • Live Environments
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling
  • Timber Recycling
  • Materials Solution Management
  • Site Preparation
  • Bulk Earthworks
  • Social Procurement

Unique Attributes

  • Australia’s biggest public transport project – consecutive early and enabling works for Martin Place Station South and North
  • Significant high rise demolition – 24 storey – and complex deep basement civil works (30m)
  • One of Sydney’s heaviest (and most critical) banks of gas, electricity, water and fibre optic mains infrastructure beneath/adjacent to tower

Key Challenges

  • Fully operational and heritage listed rail tunnels connected to basement columns of 24 storey tower, as well as within 3m of basement excavation works
  • Underpinning Heritage listed structure directly adjacent to civil works, including strict vibration controls
  • Daily monitoring and Geotechnical Mapping of over 6,000m2 of Excavated Walls
  • DELTA Group - Projects