Instagram
YouTube
LinkedIn
About
About Delta Group
Company Profile
Sustainability
News & Media
Capabilities
Contracting Capabilities
Civil Construction
Demolition
Piling
Landscaping
Environmental
Waste Management & Recycling
Heavy Plant Hire
Materials Solution Management
Sectors
Sector Capabilities
Urban
Public Infrastructure
Commercial
Residential
Health & Aged Care
Retail & Hospitality
Industrial
Renewables & Transmission
Energy
Oil & Gas
Mining & Resources
Manufacturing
Projects
Businesses
Our Businesses
Delta Group
Delta Recycling
Delta Rent
BRC Piling & Foundations
Browns Piling
CMA Contracting
Eastern Plant Hire
Earth Solutions Group
Grange Environmental
SKIPZ
Whelan the Wrecker
Widi Ngaruwa
Careers
Careers Overview
Job Vacancies
Cadet Program
Graduate Program
Contact
St Kilda Transmission Station
Hansen Yuncken
Sector: Industrial, Renewables & Transmission
>10%
Indigenous Participation
11,000m²
Asphalt
200,000t
Bulk Excavation
>3km
Haul Road & Kerbing
>1.2km
Stormwater Pipe
>12,000
Total Workhours
Enviro Controls & Monitoring
Materials Solution Management
Cultural & Heritage Surveying
Bulk & Detailed Earthworks
Haul Road Construction & Management
Backfilling & Compaction
Unique Attributes
Significant cultural heritage elements, with works led by Widi Ngaruwa (supported by Delta Group)
Bulk fill for pavement consrtruction
Haul road and kerbing construction, including asphalt – installation of 300-450mm diameter stormwater pipe
Key Challenges
Installation of 54 precast stormwater pits, both with grated inlet and steel gatic lids
Installation of various stormwater treatment systems – gross pollutant systems and hydrocarbon separators
Installation of large below ground concrete rainwater storage tanks, involving deep/detailed excavations, ground water dewatering, and crane lifts
CCTV camera inspection of all installed infrastructure
×
←
→
Back to PROJECTS