Microsoft Data Centre MEL04-05-06

Kapitol Group

Sector: Urban, Commercial

  • >80,000Total Workhours
  • 1,000m²Post Tensioned Slab
  • 150,000m³Spoil Removed/Imported
  • >30,000tACM Removed
  • 6haArea for Impact Rolling & Compaction
  • 84Pad Footing in 10 Days
  • Traffic Management
  • Enviro Monitoring & Controls
  • Piling Platform & Proof Digging
  • Ground Improvement
  • Bulk Earthworks
  • Site Remediation
  • Detailed Earthworks
  • Pad Footings
  • Permits & Authorities
  • Mechanical Demolition
  • Stakeholder Engagement
  • ACM Abatement & Removal
  • Backfilling
  • Compaction
  • Engineering (3rd Party)

Unique Attributes

  • Concurrent/consecutive work programmes across three separate packages
  • 13ha site in suburban Melbourne with significant and unforeseen friable asbestos contaminated soil requiring remediation and ground improvement works, including approved controls for load out
  • 3rd party geotech engineering engaged for impact rolling and compaction
  • Social procurement targets achieved – cadet engineer, non trade female labourer, and CALD labourers

Key Challenges

  • Maintain critical path programme while managing unforeseen remediation works – no delays
  • Extensive stakeholder engagement – neighbouring residential, businesses, local council, and regulators
  • Significant import of materials to support ground improvement measures across 13ha site footprint
  • Delivery of best practice enviro controls to mitigate ACM risk – truck wraps, haul road construction and dust suppression