Mayes Canal Bridge

Hall Contracting

Sector: Urban, Public Infrastructure

  • 3,900Total Workhours
  • >350tConcrete Recycled
  • >50Heavy Vehicle Movements
  • Hazmat Removal
  • Manual Demolition
  • Mechanical Demolition
  • Cut & Lift Demolition
  • Gantries
  • Traffic Management
  • Services
  • Cranage & Rigging
  • Propping & Bracing
  • Temp Works Engineering
  • Enviro Monitoring & Controls
  • Stakeholder Engagement
  • Live Environments
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling
  • Permits & Authorities

Unique Attributes

  • Staged demolition of pedestrian and vehicle bridges over water, with concurrent (and adjacent) construction of new four lane bridge
  • Extensive traffic management planning and coordination during demolition stages

Key Challenges

  • Strict enviro controls and monitoring to protect waterway underneath works – works area ‘wrapped’ in geofabric with pontoon located immediately below works area
  • Stage 2 programme involved heavily restricted works footprint, resulting in deployment of smaller crane and use of manual demolition methodologies such as engineered saw cuts – increasing total number of lifts but reducing impact on public use of bridge