M1 M3 Gateway Upgrade

Lendlease

Sector: Urban, Public Infrastructure

  • >6,000Total Workhours
  • 250Core Holes
  • 350mRoad Saving
  • Hazmat Removal
  • Manual Demolition
  • Mechanical Demolition
  • Cut & Lift Demolition
  • Scaffold
  • Traffic Management
  • Cranage & Rigging
  • Propping & Bracing
  • Temp Works Engineering
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling
  • Permits & Authorities
  • Enviro Monitoring & Controls
  • Stakeholder Engagement

Unique Attributes

  • Structural demolition of two lane bridge above Queensland’s busiest road – the M1 Motorway, including night works to accommodate road closures
  • Cut and lift methodology designed alongside safe removal of asbestos sheeting throughout structure
  • 450t crawler crane (with 72m long boom) deployed to lift 26m girder beams – placed onto 45m long trailers with bridge deck attached
  • Installation of scaffold tower to carry weight of structure once bridge cut in half

Key Challenges

  • Design and implementation of strict asbestos controls – gutter systems to capture slurry; placement of bins to capture core holes; core hole protection flanges for safe lifts; protective L-angles installed to protect edges; and onsite hygienist and sign offs prior to reopening motorway
  • Restricted works timeframe – 5 hours per shift – to minimise impact on motorway and neighbouring residents