Retention and excavation of 16m deep basement adjacent to Darling Harbour
Dewatering, treatment and discharge of groundwater
Installation of micro piles in basement for hydrostatic slab
Installation of piles in light rail corridor
Installation of complex structural steel walers
Jet grout installation for retention wall
Key Challenges
Live environment included major events such the International Boat Show, Vivid, and cinema (movie) premieres – as well as a full schedule of conferences and exhibitions at the adjacent ICC Sydney
Extensive public interface throughout works – Pyrmont Bridge, Sofitel Hotel, and ICC balcony
Strict enviro controls – noise/vibration/dust
Geotechnical (sub surface) conditions and presence of ground water across site
Protection of heritage listed stormwater structures