BAC Domestic Terminal

Lendlease

Sector: Urban, Commercial

  • >45,000Total Workhours
  • 2,000m²Hazmat Removed
  • 50Total Workforce at Peak
  • 46,575Domestic Terminal Passengers Per Day
  • Stakeholder Engagement
  • Permits & Authorities
  • Hazmat Removal
  • Strip Out
  • Manual Demolition
  • Mechanical Demolition
  • Robotic Demolition
  • Cut & Lift Demolition
  • Scaffold
  • Traffic Management
  • Cranage & Rigging
  • Propping & Bracing
  • Temp Works Engineering
  • Enviro Monitoring & Controls
  • Live Environments
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling

Unique Attributes

  • Domestic Terminal Building demolition in ‘live’ airport environment, including strip out changes to security systems and baggage handling areas as well as structural demolition/alteration works
  • Sequencing and programming with concurrent ‘new build’ works immediately following demolition works as crews move from one area/zone to another

Key Challenges

  • Programme based on night works due to strict noise, dust and vibration restrictions throughout operating terminal
  • Public interface work areas in close proximity to airport security services, baggage handling and other public facilities
  • High levels of manual demolition
  • Extensive stakeholder engagement – Brisbane Airport Corporation, Airlines, Terminal Staff/Businesses
  • DELTA Group - Projects
  • DELTA Group - Projects