Diversified and integrated works programme – demolition, recycling, civil and landscaping
Followed structural engineering sequence to safely demolish 12m high, multi-storey carpark to ground level, including ground slab, footings and capping beams
Civil works included inground services – hydraulic and electrical
Landscaping works included top soil levelling, grass and mulch, and reconstruction of footpaths
Key Challenges
Live (university campus) environment with high pedestrian traffic volumes within close proximity to works
Inclement weather, including high wind
Contaminated water treatment and on site separation of C&D waste to maximise resource recovery rates