Air Trunk Data Centre

Built

Sector: Urban, Commercial

  • >10,000m³Clay Spoil Removed
  • >168,000Total Workhours Over 7 Packages
  • 31,800Total Workhours
  • >13,000Heavy Vehicle Movements
  • 500Foundation Piles
  • 3,000m²Asphalt
  • 400mKerbs
  • Hoardings
  • Piling Platform & Proof Digging
  • Bulk Earthworks
  • Propping
  • Foundation Piles
  • Core Retention
  • Detailed Earthworks
  • Pad Footings
  • Pile Caps
  • Lift Rafts
  • Site Dewatering
  • Crane Base Construction
  • Slab Preparation
  • Slab On Ground
  • Hardstand Construction
  • Retaining Walls
  • Roads & Pavements
  • Manual Demolition
  • Mechanical Demolition
  • Cut & Lift Demolition
  • Traffic Management
  • Cranage & Rigging
  • Temp Works Engineering
  • Enviro Monitoring & Controls
  • Stakeholder Engagement
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling
  • Green Star Reporting
  • Permits & Authorities
  • Kerbs & Drainage
  • Line Marking
  • Mulching
  • Top Soil
  • Trees & Shrubs
  • Irrigation Systems

Unique Attributes

  • Integrated delivery of demolition, recycling, civil construction, and external (landscaping) works spanning 7 distinct work packages
  • Multiple large volume post tensioned slab pours, including high early strength concrete to maintain precast erection and accelerated programme
  • Deployment of the largest heavy lift luffing tower crane in the world – M2480D

Key Challenges

  • Extremely accelerated work programmes and coordination of large civil and landscaping handovers, including asphalt roads and soft landscaping whilst working with other trades to maintain consistent work to the main structure
  • Sequencing of extremely large (1,200m2) concrete pours with high early strength mixes and high tolerance finishes, including some areas requiring polished concrete finish
  • Design and approval of works as construction continued across site