77 Southbank Boulevard

Development Victoria

Sector: Urban, Commercial

  • 15 | 26Total Trades | Workforce At Peak
  • 21,000tC&D Waste Removed
  • >90%Resource Recovery Rate
  • >1,500Heavy Vehicle Movements
  • 5,500m2Scaffold
  • Temp Works Engineering
  • Hazmat Removal
  • Strip Out
  • Manual Demolition
  • Mechanical Demolition
  • Long Reach Demolition
  • Scaffold
  • Hoardings
  • Traffic Management
  • Services
  • Enviro Monitoring & Controls
  • Stakeholder Engagement
  • Live Environments
  • Skip Bin Hire
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling
  • Green Star Reporting
  • Permits & Authorities

Unique Attributes

  • Structural demolition of the roof slab and level 5 slab utilising small/mini plant, followed by level 4 to ground level using Long Reach excavator
  • Demolition of basement slab and walls, including backfill with mudstone to facilitate construction of a piling platform
  • Salvage of office furniture for reuse

Key Challenges

  • Interface with concurrent RACM works at Kavanaugh/Sturt Street intersections and heavy vehicle traffic management in heavily congested and densely populated ‘live’ pedestrian and high rise residential environment
  • Strict enviro controls – noise, vibrations, dust – and extensive stakeholder engagement in collaboration with client
  • Removal of significant volumes of external pre-cast concrete
  • DELTA Group - Projects