4,300tImported Recycling Materials for Pile Mat Construction
3,500m²Scaffold
>500Heavy Vehicle Movements
Piling Platform & Proof Digging
Ground Improvement
Bulk Earthworks
Site Dewatering
Slab Preparation
Hazmat Removal
Strip Out
Manual Demolition
Mechanical Demolition
Long Reach Demolition
Scaffold
Hoardings
Traffic Management
Security
Services
Cranage & Rigging
Propping & Bracing
Temp Works Engineering
Enviro Monitoring & Controls
Stakeholder Engagement
Live Environments
Skip Bin Hire
Waste Transfer
Concrete Recycling
Steel Recycling
Green Star Reporting
Permits & Authorities
Surveys – Geotechnical
Unique Attributes
Medium rise demolition using manual and mechanical methodologies – small/mini plant and 65t long reach excavator – with heavily restricted site footprint and congested access/egress
Design and installation of steel-framed edge protection to segregate the slab edges during structural demolition works
Key Challenges
Strict enviro controls and monitoring – particularly dust, vibrations and noise, with site directly adjacent to ‘live’ day care/nursery school facility, including open air playground area
RC columns and beams were poorly reinforced and concrete very weak – requiring change of methodology and deployment of smaller plant, including bespoke steel ramps for tracking between floors