Griffith University Nathan Campus

Lendlease

Sector: Urban, Commercial

  • 50,000+Total Work Hours
  • 5,000m2Full Perimeter Scaffold Encapsulation
  • 93%Resource Recovery Rate
  • 11,000tConcrete Recycled
  • Surveys – Geotechnical
  • Piling Platform & Proof Digging
  • Ground Improvement
  • Bulk Earthworks
  • Site Remediation
  • Site Dewatering
  • Inground Services
  • Slope Stabilisation
  • Stormwater & Drains
  • Roads & Pavements
  • Kerbs
  • Permits & Authorities
  • Hazmat Removal
  • Strip Out
  • Mechanical Demolition
  • Long Reach Demolition
  • Scaffold
  • Hoardings
  • Traffic Management
  • Cranage & Rigging
  • Propping & Bracing
  • Temp Works Engineering
  • Enviro Monitoring & Controls
  • Stakeholder Engagement
  • Live Environments
  • Social Procurement
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling
  • Green Star Reporting

Unique Attributes

  • Integrated demolition, recycling and civil works program – consecutive and concurrent programming and sequencing
  • Demolition of 5,000m2 structure – including hazmat removal – within a live university campus
  • Heavy scaffold encapsulation as a result of friable asbestos contamination – full exterior of structure and weighing 500 tonnes
  • Improvised ground gutter system to control run off
  • Third party geotech and structural engineering for deployment of heavy machines and limited ground bearing capacity of campus road infrastructure

Key Challenges

  • Live university environment – including five buildings and food court
  • Restricted site access limited deployment of heavy plant – extensive traffic management
  • Enviro controls – particularly dust control measures and monitoring; water run off measures to protect adjacent creek