Protection, retention and relocation of more than 70 significant trees, including tree protection zones across 16,000m2 site and erection of 12 metre high scaffolding
Installation of 409lm of 2.4 metre high perimeter hoarding concurrently with the demolition staging
Demolition and removal of all slabs and footings throughout multiple structures
Key Challenges
Temp works engineering for disconnection of sections of structure
Resourcing and sequencing of concurrent high reach (mechanical) demolition works
Installation of Bondor panelling for weatherproofing remaining structure (for an additional five year period)
Construction of a temporary rubble batter to support and maintain existing retaining wall