200tMobile Crane Deployed for Cut & Lift Demolition Works
11-17tSlag Troughs Cut and Lifted
Live Environments
Enviro Controls & Monitoring
Cranage & Rigging
Mechanical Demolition
Ferrous Steel
Non Ferrous Steel
Materials Solution Management
Waste Transfer
Unique Attributes
Two stage demolition works program involving manufacturing infrastructure at Olympic Dam Mine in remote Roxby Downs, South Australia
Demolition of ‘Old Gold Room’ structure – steel framed, tin clad shed and adjoining concrete strong room
Demolition of Slag Floats infrastructure – hoppers and sump pumps; flotation rougher cells and associated structures
Key Challenges
Mixture of multiple contaminants and hazardous substances, including NORMs, Xanthate, hydrocarbons, Neutral Pulp and other process contaminants – all C&D waste sent to CWDF for processing, cleaning and categorisation
Design and install of temporary retention to allow for diversion of existing services
Cut and lift methodologies required to accommodate adjacent live operations