Next CD M2 Data Centre

Kapitol Group

Sector: Urban, Commercial

  • >1,700m³Concrete Poured
  • >5,100Total Workhours
  • 38Foundation Piles
  • Piling Platform & Proof Digging
  • Bulk Earthworks
  • Site Remediation
  • Shotcrete Walls
  • Foundation Piles
  • Pad Footings
  • Pile Caps
  • Lift Rafts
  • Crane Base Construction
  • Slab Preparation
  • Waterproofing
  • Traffic Management
  • Enviro Monitoring & Controls
  • Detailed Earthworks
  • Permits & Authorities
  • Stakeholder Engagement

Unique Attributes

  • Sequential construction of in-ground foundations due to challenging site footprint and access
  • Challenging geotech ground conditions – hard rock
  • Piling solution designed to accommodated tensile loads

Key Challenges

  • Detailed excavations in hard rock presented programme risks that were mitigated with specialist equipment
  • Civil works programme delivered concurrently alongside electrical and plumbing contractors