Microsoft Data Centre MEL07

BESIX Watpac

Sector: Urban, Commercial

  • >137,000m³Clay Spoil Removed
  • >140,000m³Subbase Imported
  • >13,000Heavy Vehicle Movements
  • 31,800Total Workhours
  • 40Total Workforce at Peak
  • Traffic Management
  • Enviro Monitoring & Controls
  • Piling Platform & Proof Digging
  • Ground Improvement
  • Bulk Earthworks
  • Site Remediation
  • Foundation Piles
  • Detailed Earthworks
  • Inground Services
  • Hardstand Construction
  • Retaining Walls
  • Stormwater & Drains
  • Roads & Pavements
  • Kerbs
  • Permits & Authorities
  • Pit Installation
  • Line Marking
  • Pavements
  • Subbases
  • Stairs
  • Outdoor Furniture
  • Surfacing – Turf
  • Mulching
  • Top Soil
  • Trees & Shrubs
  • Irrigation Systems
  • Stakeholder Engagement

Unique Attributes

  •  Multi-stage civil construction and landscaping work packages
  • Over 2.5km of 3m+ deep trenching across the entire site while works were being completed on the building – requiring close coordination and combination of trenching and benching to allow works to continue around site
  • Significant amount of unsuitable ground that required removal and import of suitable material for back fill under Level 1 supervision

Key Challenges

  • Urgent remediation of entire site was completed to facilitate installation of structure and critical power and data cables