Instagram
YouTube
LinkedIn
About
About Delta Group
Company Profile
Sustainability
News & Media
Capabilities
Contracting Capabilities
Civil Construction
Demolition
Piling
Landscaping
Environmental
Waste Management & Recycling
Heavy Plant Hire
Materials Solution Management
Sectors
Sector Capabilities
Urban
Public Infrastructure
Commercial
Residential
Health & Aged Care
Retail & Hospitality
Industrial
Renewables & Transmission
Energy
Oil & Gas
Mining & Resources
Manufacturing
Projects
Businesses
Our Businesses
Delta Group
Delta Recycling
Delta Rent
BRC Piling & Foundations
Browns Piling
CMA Contracting
Eastern Plant Hire
Earth Solutions Group
Grange Environmental
SKIPZ
Whelan the Wrecker
Widi Ngaruwa
Careers
Careers Overview
Job Vacancies
Cadet Program
Graduate Program
Contact
Melbourne Arts Centre
Lendlease
Sector: Urban, Public Infrastructure
8,000
Workhours
98%
Resource Recovery Rate
>2,500t
Concrete Removed
368t
Heaviest Design Lift
58
Reinforced Concrete “T” Beams Demolished
1.2km+
Of Road-Sawing
100t | 272t
Post Tensioned Beams Removed
Traffic Management
Enviro Monitoring & Controls
Temp Works Engineering
Strip Out
Manual Demolition
Mechanical Demolition
Cut & Lift Demolition
Scaffold
Hoardings
Heritage Protection
Services
Cranage & Rigging
Live Environments
Stakeholder Engagement
Unique Attributes
Design, fabrication, and use of bespoke gantry system to facilitate removal of beams and demolition of decks
Use of Doolan’s Heavy Lift and Lock Gantry System to remove 100t and 272t Post Tensioned beams
Construction of mobile crane platforms
Removal of inground pile caps and associated retaining wall, including reinstatement of pile cap excavations
Works undertaken in a ‘live’ (arts centre) environment
Key Challenges
Noise and vibration sensitive demolition methodology to protect adjoining heritage listed structures, including rubber tracks on 47t excavators
5.5 Star NABERS and 5 Star Greenstar rating requirements, including tracking and reporting
Traffic management and supervision, with major road and pedestrian thoroughfare closures to facilitate deck removals
Transport offsite of all demolished material, including individual precast elements weighing over 70t each
×
←
→