Esso House

Savills

Sector: Urban, Commercial

  • 20 | 30Total Trades | Workforce at Peak
  • 45,000tC&D Waste Removed
  • >90%Resource Recovery Rate
  • >3,500Heavy Vehicle Movements
  • 20,000m²Scaffold
  • Traffic Management
  • Hazmat Removal
  • Strip Out
  • Manual Demolition
  • Mechanical Demolition
  • Long Reach Demolition
  • Scaffold
  • Hoardings
  • Services
  • Cranage & Rigging
  • Temp Works Engineering
  • Enviro Monitoring & Controls
  • Stakeholder Engagement
  • Live Environments
  • Skip Bin Hire
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling
  • Permits & Authorities

Unique Attributes

  • Erection of full height 65m high perimeter scaffold – off needles
  • Installation and erection of Tower Crane within existing structure lift shaft
  • Structure consisted of full glazed facade with pre-cast perimeter columns

Key Challenges

  • Extensive stakeholder engagement – neighbouring five star hotel (The Langham)
  • Strict enviro controls – noise, vibrations, dust
  • Sequencing of small/mini plant to undertake floor-by-floor demolition
  • Heavy vehicle movements in high pedestrian traffic location and heavily congested inner city environment