Australian Catholic University Campus Park

Australian Catholic University

Sector: Urban, Commercial

  • >23,000Total Workhours
  • >90%Resource Recovery Rate
  • >500m²Scaffold
  • 180m³Concrete Poured
  • 3,290Total Plants
  • >200m²Paving Installed
  • Ground Improvement
  • Capping Beams
  • Pad Footings
  • Inground Services
  • Waterproofing
  • Slab On Ground
  • Retaining Walls
  • Stormwater & Drains
  • Roads & Pavements
  • Kerbs
  • Strip Out
  • Mechanical Demolition
  • Long Reach Demolition
  • Cut & Lift Demolition
  • Scaffold
  • Traffic Management
  • Cranage & Rigging
  • Propping & Bracing
  • Temp Works Engineering
  • Waste Transfer
  • Concrete Recycling
  • Steel Recycling
  • Green Star Reporting
  • Permits & Authorities
  • Bulk Earthworks
  • Detailed Earthworks
  • Recreational Facilities
  • Outdoor Furniture
  • Surfacing – Turf
  • Surfacing – Grass
  • Planters
  • Mulching
  • Top Soil
  • Trees & Shrubs
  • Irrigation Systems
  • Live Environments
  • Enviro Monitoring & Controls
  • Stakeholder Engagement

Unique Attributes

  • Diversified and integrated works programme – demolition, recycling, civil and landscaping
  • Followed structural engineering sequence to safely demolish 12m high, multi-storey carpark to ground level, including ground slab, footings and capping beams
  • Civil works included inground services – hydraulic and electrical
  • Landscaping works included top soil levelling, grass and mulch, and reconstruction of footpaths

Key Challenges

  • Live (university campus) environment with high pedestrian traffic volumes within close proximity to works
  • Inclement weather, including high wind
  • Contaminated water treatment and on site separation of C&D waste to maximise resource recovery rates
  • DELTA Group - Projects