500tStructural Steel Installed for Heritage Facade Retention
28,500m²Lead Paint Removed
Enviro Monitoring & Controls
Permits & Authorities
Hazmat Removal
Strip Out
Manual Demolition
Mechanical Demolition
Scaffold
Gantries
Hoardings
Traffic Management
Heritage Protection
Services
Propping & Bracing
Temp Works Engineering
Stakeholder Engagement
Live Environments
Waste Transfer
Concrete Recycling
Steel Recycling
Timber Recycling
Site Preparation
Security
Unique Attributes
Highly visible and restricted/congested site location in Sydney CBD
Accelerated programme to accommodate delays incurred during the COVID-19 Pandemic
Heritage salvage and protection of 500+ items, including awnings, subway tiles, lift indicators, travertine
Temporary Works engineering and design – structural steel retention of heritage listed facade
Key Challenges
80 year old heritage listed facade requiring extensive protection/retention systems, bespoke methodologies and fabrication techniques were successfully employed to connect new and old steel
Significant client and developer involvement/liaison; multiple large crews across 15 different floors and interface between contractors; strict environmental controls – noise, vibrations and dust; and extensive traffic management planning and key stakeholder engagement